Planning the main board for a new building
What to decide early, what to send your board builder, and the common mistakes that cost time on site.
The main low voltage board is one of the first big items a new building needs and one of the last to be thought about. When it is planned late, it ends up squeezed into a room that is too small, ordered on a tight lead time, or changed after it is built. This post covers what to decide early so the board arrives right first time.
Start with the load
Everything follows from how much power the building needs and where it goes. Before a board can be designed, the electrical engineer will usually prepare:
- a load schedule, listing each part of the building and its expected demand
- a single line diagram, showing how the power flows from the supply to each circuit
- the supply details, including the rating and the expected fault level
If any of these are still rough, that is fine for a first conversation. A board builder can give useful feedback on a draft. They just need to be firm before the board goes into production.
Decide on the supply arrangement
Ask early:
- Will the building be fed from the utility, from its own transformer, or both?
- Will there be a standby generator? If so, does it back up the whole building or only essential loads?
- Is solar or battery storage planned, now or later?
Each of these changes the shape of the board. A generator usually means a changeover arrangement and possibly a split busbar for essential and non essential supply. Solar may need its own connection point and protection. Planning these in from the start is far cheaper than adding them later.
Choose the form of separation
The form of separation affects the size, the cost and how easy the board is to maintain. Buildings that cannot be shut down easily, such as hospitals and large offices, usually need a higher form. Our post on forms of separation explains the options.
Plan the room before the board
The most common problem we hear about is a plant room that is too small. When sizing the room, think about:
- Width and depth of the board, including any future extension
- Clearance in front for doors to open fully and for people to work safely
- Clearance behind or beside, if the board needs rear or side access
- Cable entry: will cables come in from the top, from below through a trench, or both?
- Access route: can the board actually get into the room? Check door widths, lifts, ramps and corners. Large boards can be built in sections that are joined on site, but this needs to be known early.
- Ventilation, since boards produce heat, especially when heavily loaded
Leave room to grow
Buildings change. Tenants move in and out, new equipment arrives, and loads grow. A board with no spare capacity can be costly to extend. As a rule of thumb, discuss spare and space ways with your engineer at design stage rather than after the fact.
Think about metering
Decide what needs to be measured:
- the whole building
- each tenant or each floor
- large individual loads such as chillers or lifts
Metering is easy to add on the drawing and harder to add once the board is built.
Lead times
A main board is built to order. The time it takes depends on the size of the board, how quickly drawings are approved, and the availability of the devices that go inside it. Large breakers in particular can have long lead times. Bring the board builder in early so the programme reflects reality. [CONFIRM: Nedlog's typical lead times, if Nedlog wants to share them.]
What to send your board builder
To get an accurate quote, send:
- The single line diagram, even in draft
- The load schedule
- The specification, if there is one
- The plant room layout, with dimensions
- Any preferences for devices or form of separation
- Your programme dates
Common mistakes
- Approving drawings late, which pushes the build date back
- Changing feeders after the board is built
- Forgetting the generator or solar connection
- A room that the board cannot physically be moved into
- No spare ways at all
In short
Plan the supply, the room and the spare capacity early. Send the drawings as soon as you have them, even in draft. The earlier the board builder is involved, the fewer surprises there are when the board arrives on site.